Name
Bartestree with Lugwardine Group Neighbourhood Development Plan
Parishes in neighbourhood area
Bartestree, Lugwardine
Current stage

The Neighbourhood Development Plan has been adopted. The plan is currently being reviewed, and has reached examination stage.

Dates of each stage
  • Neighbourhood area application date: 16 July 2012
  • Designation date: 6 September 2012
  • Regulation 14 draft plan submitted: 19 November 2015
  • Regulation 16 plan submitted: 16 March 2016
  • Plan sent for examination: 9 June 2016
  • Date of referendum: 3 November 2016
  • Date reviewed Regulation 14 draft plan submitted: 8 April 2022
  • Date reviewed Regulation 16 plan submitted: 13 October 2022
  • Date reviewed plan sent for examination: 8 December 2022
Website
Pre-draft plan stage
Adoption stage

The Bartestree with Lugwardine Neighbourhood Development Plan was made on 1 December 2016. It now forms part of the Development Plan for Herefordshire.

Reviewed Plan: Regulation 14 draft plan stage

Bartestree with Lugwardine Group Parish Council submitted their reviewed draft Neighbourhood Development Plan to Herefordshire Council on 8 April 2022.

The consultation ran from 11 April to 30 May 2022.

Reviewed Plan: Regulation 16 plan stage
Reviewed Plan: Examination stage

The Bartestree with Lugwardine Group Neighbourhood Development Plan was sent for examination on 8 December 2022. We are awaiting the examiners report.