Bosbury and Catley Group Neighbourhood Development Plan

Name
Bosbury and Catley Group Neighbourhood Development Plan
Parishes in neighbourhood area
Bosbury (part of)
Current stage

The Neighbourhood Development Plan is adopted.

Dates of each stage
  • Neighbourhood area application date: 8 June 2014
  • Designation date: 1 August 2014
  • Regulation 14 draft plan submitted: 18 December 2014
  • Regulation 16 plan submitted: 6 March 2015 (withdrawn), 9 November 2016 (re-submitted), 8 June 2018 (second re-submission)
  • Plan sent for examination: 17 January 2017 resubmitted: 16 August 2018
  • Date of referendum: 11 July 2019
Website
Pre draft plan stage
Regulation 14 draft plan stage

Bosbury and Coddington Group Parish Council submitted their draft Neighbourhood Development Plan to Herefordshire Council on 18 December 2014.

The consultation ran from 18 December to 12 February 2014.

Regulation 16 plan stage

Bosbury and Coddington Group Parish Council submitted their Neighbourhood Development Plan to Herefordshire Council on 6 March 2015.

The consultation ran from 14 May to 25 June 2015.

Bosbury and Coddington Group Parish Council formally withdrew these plans on 9 November 2016.

Regulation 16 plan re submission stage
Regulation 16 plan second re submission stage

Bosbury and Coddington Group Parish Council re-submitted their Neighbourhood Development Plan to Herefordshire Council on 8 June 2018.

The consultation ran from 15 June to 27 July 2018.

Examination stage

The Bosbury Neighbourhood Development Plan was sent for examination on 17 January 2017. The examiner's report was received on 16 March 2017.

Re examination stage
Referendum stage
Regulation 14 plan stage

The Bosbury & Catley Neighbourhood Development Plan was made on 16 August 2019. It now forms part of the Development Plan for Herefordshire.