Current stage

The Neighbourhood Development Plan has been adopted.

Dates of each stage
  • Neighbourhood area application date: 27 June 2013
  • Designation date: 27 August 2013
  • Regulation 14 draft plan submitted: 2 January 2015
  • Regulation 16 plan submitted: 6 July 2016
  • Plan sent for examination: 16 September 2016
  • Date of referendum: 7 September 2017
Website
Pre-draft plan stage
Regulation 14 draft plan stage

Kingsland Parish Council submitted their draft Neighbourhood Development Plan to Herefordshire Council on 2 January 2015.

The consultation ran from 17 December 2014 to 10 February 2015.

Regulation 16 plan stage

Kingsland Parish Council submitted their Neighbourhood Development Plan to Herefordshire Council on 9 November 2015.

The consultation ran from 17 November 2015 to 22 August 2016.

Kingsland Parish Council formally withdrew these plans on 8 July 2016.

Regulation 16 plan re-submission stage
Examination stage
Referendum stage
Adoption stage