Much Birch Neighbourhood Development Plan

Name
Much Birch Neighbourhood Development Plan
Parishes in neighbourhood area
Much Birch
Current stage

The Neighbourhood Development Plan is adopted.

Dates of each stage
  • Neighbourhood area application date: 12 July 2016
  • Designation date: 16 August 2016
  • Regulation 14 draft plan submitted: 9 December 2019
  • Regulation 16 plan submitted: 15 April 2020
  • Plan sent for examination: 22 July 2020
  • Date of referendum: 6 May 2021
Website
Pre draft plan stage
Regulation 14 draft plan stage

Much Birch Parish Council submitted their draft Neighbourhood Development Plan to Herefordshire Council on 9 December 2019.

The consultation ran from 16 December 2019 to 11 February 2020.

Regulation 14 draft plan re submission stage
Regulation 16 plan stage

The Much Birch Neighbourhood Development Plan was sent for examination on 22 July 2020. We are awaiting the examiner's report. We received the examiners report on 18 January 2021.

Regulation 16 plan re submission stage
Regulation 16 plan second re submission stage
Examination stage