Aymestrey Neighbourhood Development Plan

Name
Aymestrey Neighbourhood Development Plan
Parishes in neighbourhood area
Aymestrey
Current stage

The Neighbourhood Development Plan is adopted.

Dates of each stage
  • Neighbourhood area application date: 26 November 2015
  • Designation date: 7 January 2016
  • Regulation 14 draft plan submitted: 20 March 2018
  • Regulation 16 plan submitted: 19 June 2018
  • Plan sent for examination: 4 September 2018
  • Date of referendum: 30 May 2019
Website
Pre draft plan stage
Regulation 14 draft plan stage

Aymestrey Parish Council submitted their draft Neighbourhood Development Plan to Herefordshire Council on 20 March 2018.

The consultation ran from 19 March to 12 May 2018.

Regulation 16 plan stage

Aymestrey Parish Council submitted their Neighbourhood Development Plan to Herefordshire Council on 19 June 2018.

The consultation ran from 27 June to 22 August 2018.

Examination stage
Referendum stage
Regulation 14 plan stage
Regulation 16 stage