Herefordshire Council has secured an order requiring the owner of 14 High Street, Ledbury, to carry out works needed to remove the danger posed by the building.
The First-tier Tribunal found in favour of the council following action under Section 77 of the Building Act 1984, which allows councils to take formal action requiring an owner to make a dangerous building or structure safe. The order sets timescales for the owner to seek the necessary listed building consent and complete the specified works.
If the owner does not comply with the order, the council is authorised to carry out the works in default and seek to recover the associated costs.
The Tribunal also agreed with the council’s application for costs and ordered the owner to reimburse the full tribunal hearing fee, recognising that the owner’s failure to undertake the requested works had made the application necessary.
The decision follows a long-running case concerning safety at the rear of the High Street property. In 2025, the council confirmed that Building Control was pursuing the Section 77 process after a collapse and unsuccessful attempts to reach a satisfactory resolution with the owner.
The outcome follows extensive work by council teams, including technical evidence, legal input, preparation for hearings and coordination across services. Subject to the owner complying with the order and completing the required works, the property could subsequently be removed from the council’s Problem Property Board list.
Councillor Elissa Swinglehurst, Deputy Leader of Herefordshire Council, said:
“This is good news for Ledbury and a positive outcome after a great deal of determined work by colleagues across the council.
“Our priority throughout has been public safety. Where a dangerous building is not made safe voluntarily, the council has powers available to protect residents, businesses and visitors, and this result shows that we will use them when necessary.
“I would like to thank everyone involved for their professionalism and persistence. However, this is not the end of the story - we now want to see the required works completed so this long-standing issue can be resolved and we can support the continued regeneration and vitality of Ledbury town centre.”
Published: Friday 20 November 2026