Path Closure Orders

Photo showing a footpath closure sign Public rights of way can be temporarily closed for a variety of reasons such as special events, maintenance works, construction works, etc.  Paths can remain closed for periods of time ranging from 1 day to 6 months.  It is always preferable for the applicant to provide an alternative route for path users if possible.

For further information or a path closure application form please call 01432 261800

Special Events Closures

Such a closure can last for up to three days, and only one such closure can occur on a public right of way per year.

Please note that we will require at least 3 weeks notice to prepare and seal the Order.

5 Day Closure for Works

Where works are proposed to be executed on or near a public right of way it may be necessary for the safety and convenience of path users to close the footpath. Under the Road Traffic Regulation Act 1984 section 15(7) a path can be closed for this purpose for up to 5 days. 

There is a charge for such closures. We require a minimum notice period of 7 days before the path is to be closed in order to prepare notices.

A 5 day closure notice cannot be extended other than by arranging for a 6 month temporary closure order (see below).

6 Month Temporary Closure

In instances where a 5 day closure will not be sufficient to carry out maintenance / construction works then an order can be obtained for up to 6 months.  For these orders at least 6 weeks notice must be given (unless it is an extension to the above 5 day notice). 

There is an administration cost for a 6 month closure.  The fact that the path is going to be closed for such a long time period also involves 2 newspaper advertisements.  Advertisement costs are included in our total cost.

If works are not completed before the 6 month closure expires a further 6 month closure can be granted (up to a maximum of 3 extensions).  Each extension costs £150 and we require 6 weeks notice to process the extension application.

To view all current path closure orders click on Legal Notices.


 